Confidential Power Station (WA)

Client

Legacy Power Station (Confidential), WA

Scale

4 × 250 MW generating units (coal-fired facility)

Capital Value

>A$100 million refurbishment program

Role

Project Controls & HSEQ Specialist

Overview

A major Western Australian power station required a complex turnaround to address operational inefficiencies and extend asset life. PARX ENERGY was brought in to deliver project controls, safety governance, and industrial relations support during the high-risk outage period.

Key Contributions

  • Integrated Scheduling & Cost Controls – Implemented a unified project controls system to manage multiple workstreams.

  • HSEQ Governance – Introduced site-wide safety frameworks, toolbox talks, and audit processes.

  • Critical Path Risk Management – Identified and mitigated turbine refurbishment risks to protect schedule and budget.

  • Industrial Relations (IR) Plan – Embedded proactive union and workforce engagement strategies to maintain site stability.

Impact

  • Increased plant uptime by 18% post-turnaround.

  • Shortened outage duration by 4 weeks, reducing downtime and costs.

  • Prevented A$5 million in potential liquidated damages.

  • Delivered the project with Zero Harm—no lost-time incidents.

Outcome

Through rigorous controls, safety leadership, and proactive workforce engagement, PARX ENERGY transformed a high-risk turnaround into a safe and efficient success, restoring operational performance and extending the facility’s lifespan.